Water Street Substation Upgrade
Sobre o proxecto
This project will replace old electrical equipment with new equipment at an existing substation in Hanover, MA.
The project is now in the design phase, and the team is gathering information from fieldwork to plan construction. As the project progresses towards construction, nearby neighbors will receive more details and updates.
Beneficios do proxecto
Recursos do proxecto
Preguntas frecuentes
8 FAQsThe substation upgrade is scheduled to begin in the Spring of 2027 and be complete by the Fall of 2028. Pre-construction activities associated with the design of the project including field investigations are ongoing.
This project is taking place within National Grid’s substation located at 191 Water Street in Hanover.
A strong electrical transmission and distribution system is vital to our region’s safety, security, and economic prosperity. It is necessary for National Grid to maintain and upgrade the aging infrastructure that supports electric lines to secure the safe transmission of electricity throughout the region.
No. This work will be managed so that service interruptions are not planned.
You will likely see an increase in material and equipment deliveries in and out of the substation.
National Grid is undertaking extensive community outreach to inform neighbors, public officials, and other impacted stakeholders about the project.
No. All activities are planned to take place within the existing National Grid substation and adjacent established utility corridors.
Se tes algunha pregunta ou preocupación sobre o proxecto, ponte en contacto con:
Rylie Murray
Stakeholder Specialist
Correo electrónico:
[email protected]
Teléfono: +1-781-250-9952
Contacta connosco
Sobre o proxecto
This project will replace old electrical equipment with new equipment at an existing substation in Hanover, MA.
The project is now in the design phase, and the team is gathering information from fieldwork to plan construction. As the project progresses towards construction, nearby neighbors will receive more details and updates.
Beneficios do proxecto
By replacing and upgrading existing equipment, the substation will provide more reliable electric service and work more efficiently across the region.
Recursos do proxecto
Novas e actualizacións
Preguntas frecuentes
8 FAQsThe substation upgrade is scheduled to begin in the Spring of 2027 and be complete by the Fall of 2028. Pre-construction activities associated with the design of the project including field investigations are ongoing.
This project is taking place within National Grid’s substation located at 191 Water Street in Hanover.
A strong electrical transmission and distribution system is vital to our region’s safety, security, and economic prosperity. It is necessary for National Grid to maintain and upgrade the aging infrastructure that supports electric lines to secure the safe transmission of electricity throughout the region.
No. This work will be managed so that service interruptions are not planned.
You will likely see an increase in material and equipment deliveries in and out of the substation.
National Grid is undertaking extensive community outreach to inform neighbors, public officials, and other impacted stakeholders about the project.
No. All activities are planned to take place within the existing National Grid substation and adjacent established utility corridors.
Se tes algunha pregunta ou preocupación sobre o proxecto, ponte en contacto con:
Rylie Murray
Stakeholder Specialist
Correo electrónico:
[email protected]
Teléfono: +1-781-250-9952