Water Street Substation Upgrade
Oor die Projek
This project will replace old electrical equipment with new equipment at an existing substation in Hanover, MA.
The project is now in the design phase, and the team is gathering information from fieldwork to plan construction. As the project progresses towards construction, nearby neighbors will receive more details and updates.
Projekvoordele
Projekhulpbronne
Gereelde vrae
8 FAQsThe substation upgrade is scheduled to begin in the Spring of 2027 and be complete by the Fall of 2028. Pre-construction activities associated with the design of the project including field investigations are ongoing.
This project is taking place within National Grid’s substation located at 191 Water Street in Hanover.
A strong electrical transmission and distribution system is vital to our region’s safety, security, and economic prosperity. It is necessary for National Grid to maintain and upgrade the aging infrastructure that supports electric lines to secure the safe transmission of electricity throughout the region.
No. This work will be managed so that service interruptions are not planned.
You will likely see an increase in material and equipment deliveries in and out of the substation.
National Grid is undertaking extensive community outreach to inform neighbors, public officials, and other impacted stakeholders about the project.
No. All activities are planned to take place within the existing National Grid substation and adjacent established utility corridors.
Indien u enige vrae of bekommernisse oor die projek het, kontak asseblief:
Rylie Murray
Stakeholder Specialist
E-pos:
[email protected]
Foon: +1-781-250-9952
Kontak Ons
Oor die Projek
This project will replace old electrical equipment with new equipment at an existing substation in Hanover, MA.
The project is now in the design phase, and the team is gathering information from fieldwork to plan construction. As the project progresses towards construction, nearby neighbors will receive more details and updates.
Projekvoordele
By replacing and upgrading existing equipment, the substation will provide more reliable electric service and work more efficiently across the region.
Projekhulpbronne
Nuus en opdaterings
Gereelde vrae
8 FAQsThe substation upgrade is scheduled to begin in the Spring of 2027 and be complete by the Fall of 2028. Pre-construction activities associated with the design of the project including field investigations are ongoing.
This project is taking place within National Grid’s substation located at 191 Water Street in Hanover.
A strong electrical transmission and distribution system is vital to our region’s safety, security, and economic prosperity. It is necessary for National Grid to maintain and upgrade the aging infrastructure that supports electric lines to secure the safe transmission of electricity throughout the region.
No. This work will be managed so that service interruptions are not planned.
You will likely see an increase in material and equipment deliveries in and out of the substation.
National Grid is undertaking extensive community outreach to inform neighbors, public officials, and other impacted stakeholders about the project.
No. All activities are planned to take place within the existing National Grid substation and adjacent established utility corridors.
Indien u enige vrae of bekommernisse oor die projek het, kontak asseblief:
Rylie Murray
Stakeholder Specialist
E-pos:
[email protected]
Foon: +1-781-250-9952