U2 ACR

Transmission Line Project

परियोजना के बारे में

The U2 Transmission Line is 3.5 miles long and runs through Stoughton, Brockton, and Easton. The line was built in the 1970’s and has not had major upgrades since then. This project will add optical ground wire and improve the line’s condition to provide safe and reliable power to customers. Optical ground wire is a type of fiber-optic cable made of steel and aluminum used on overhead power lines to protect them from lightning and carry high-speed data and communication signals. Replacing the power lines will also increase capacity to meet future energy needs.

परियोजना के लाभ

2023
  • Aug - Gate A Approval
2024
2025
  • Feb - Gate B
  • Apr - Kick-Off Meeting
2026
  • Feb - Soil Borings
2027
  • Jan - Gate C Approval
2028
  • Jan - Engineering and Design Completed
  • Apr - Gate C1 Approval
2029
  • Jan - All Permits In Hand
  • Feb - Construction Begins
2030
  • Nov - Overall Ready for Load
  • Dec - Construction Complete
2031
  • Jun - Project Schedule Closed

हमसे संपर्क करें

    * एक आवश्यक फ़ील्ड इंगित करता है

    परियोजना के बारे में

    The U2 Transmission Line is 3.5 miles long and runs through Stoughton, Brockton, and Easton. The line was built in the 1970’s and has not had major upgrades since then. This project will add optical ground wire and improve the line’s condition to provide safe and reliable power to customers. Optical ground wire is a type of fiber-optic cable made of steel and aluminum used on overhead power lines to protect them from lightning and carry high-speed data and communication signals. Replacing the power lines will also increase capacity to meet future energy needs.

    परियोजना के लाभ

    समाचार और अपडेट

    समय

    2023
    2024
    2025
    2026
    2027
    2028
    2029
    2030
    2031
    2032
    Gate A Approval
    08/2023 – 08/2023
    Gate B
    02/2025 – 02/2025
    Kick-Off Meeting
    04/2025 – 04/2025
    Soil Borings
    02/2026 – 02/2026
    Gate C Approval
    01/2027 – 01/2027
    Engineering and Design Completed
    01/2028 – 01/2028
    Gate C1 Approval
    04/2028 – 04/2028
    All Permits In Hand
    01/2029 – 01/2029
    निर्माण
    02/2029 – 12/2030
    Overall Ready for Load
    11/2030 – 11/2030
    Project Schedule Closed
    06/2031 – 06/2031

    हमसे संपर्क करें

      * एक आवश्यक फ़ील्ड इंगित करता है