Pembroke Substation

About the Project

In 2019, National Grid studied the electric system in and around Hanover to assess reliability, safety, and equipment needs across multiple substations. The study found that building a new 115-kilovolt substation in Pembroke, which currently has no substation, would best meet local power needs. Building a substation at this location would improve reliability for Pembroke and nearby communities by adding a third transmission supply and connecting to Eversource’s 191 line. The project would also add four feeder ties to improve safety and make power delivery more reliable. Overall, the new substation would provide faster and more dependable electric service, especially by allowing for quicker restoration during outages.

Project Benefits

News and Updates

Coming Soon.

2024
  • Dec - Initiate Zoning Permitting Begins
2025
2026
2027
2028
  • Jan - Local Permitting - Zoning / Special Permit Approved Begins
2029
  • Apr - All Permits in Hand Begins
  • Nov - Construction Begins
2030
2031
  • Nov - Construction Complete

Phases of Construction

  1. Site Preparation

    The first step is removing buildings, trees, and brush as needed. This work allows construction crews to safely build access roads and remove trees that could fall onto the power line.

  1. Environmental Controls

    Next, steps are taken to protect the area during construction. These may include placing mats, silt fences, and concrete washout containers.

  1. Substation Construction

    The construction phase involves preparing the site, installing foundations, erecting structures, and installing electrical equipment such as transformers, circuit breakers, busbars, control systems, and protection systems. Construction also includes cable installation, grounding, fencing, access roads, and drainage. After installation, the substation is inspected, tested, commissioned, and connected to the electricity network. Safety, environmental controls, quality assurance, and regulatory compliance are maintained throughout the work.

  1. Restoration

    Once construction is finished, crews will restore the work areas to their original condition as much as possible, unless permits or land agreements specify otherwise.

    * Indicates a required field

    About the Project

    In 2019, National Grid studied the electric system in and around Hanover to assess reliability, safety, and equipment needs across multiple substations. The study found that building a new 115-kilovolt substation in Pembroke, which currently has no substation, would best meet local power needs. Building a substation at this location would improve reliability for Pembroke and nearby communities by adding a third transmission supply and connecting to Eversource’s 191 line. The project would also add four feeder ties to improve safety and make power delivery more reliable. Overall, the new substation would provide faster and more dependable electric service, especially by allowing for quicker restoration during outages.

    Project Benefits

    Transmission Line Icon

    Improved reliability – The new substation will provide safer and more reliable electric service to customers in the area.

    Hardhat Icon

    Faster outage response – Customers in Pembroke will see quicker response times during outages because crews will be able to isolate problems and restore power more quickly.

    Cityscape Icon

    Meets growing energy demand – The new 115-kilovolt substation will help meet the growing demand for electricity in Massachusetts.

    Timeline

    2024
    2025
    2026
    2027
    2028
    2029
    2030
    2031
    2032
    Initiate Zoning Permitting
    12/2024 – 12/2024
    Local Permitting - Zoning / Special Permit Approved
    01/2028 – 01/2028
    All Permits in Hand
    04/2029 – 04/2029
    Construction
    11/2029 – 11/2031

    Phases of Construction

    1. Site Preparation

      The first step is removing buildings, trees, and brush as needed. This work allows construction crews to safely build access roads and remove trees that could fall onto the power line.

    1. Environmental Controls

      Next, steps are taken to protect the area during construction. These may include placing mats, silt fences, and concrete washout containers.

    1. Substation Construction

      The construction phase involves preparing the site, installing foundations, erecting structures, and installing electrical equipment such as transformers, circuit breakers, busbars, control systems, and protection systems. Construction also includes cable installation, grounding, fencing, access roads, and drainage. After installation, the substation is inspected, tested, commissioned, and connected to the electricity network. Safety, environmental controls, quality assurance, and regulatory compliance are maintained throughout the work.

    1. Restoration

      Once construction is finished, crews will restore the work areas to their original condition as much as possible, unless permits or land agreements specify otherwise.