Charlton to Sturbridge Interconnection
Projek
Oor die Projek
The Charlton to Sturbridge Interconnection Project will connect a solar power site in Charlton to National Grid’s electric system. Approximately 3.5 miles of work will take place from North Sturbridge Road to Podunk Road. Crews will install new utility poles and power lines in Charlton and Sturbridge. Some limited areas of work will also take place on Charlton Road and Picker Road.
Projekvoordele
Projekhulpbronne
2023
- Spring - Project Engagement Begins
- Spring - Field Assessments Begins
- Spring - Permitting Begins
2024
2025
- Jan - Vegetation Management Begins
- Fall - Construction and Restoration Begins
- Dec - Vegetation Management Complete
2026
- September - Construction and Restoration Complete
- Deurlopend - Projekbetrokkenheid voltooi
- Deurlopend - Veldassesserings voltooi
- Ongoing - Permitting Complete
Kontak Ons
Oor die Projek
The Charlton to Sturbridge Interconnection Project will connect a solar power site in Charlton to National Grid’s electric system. Approximately 3.5 miles of work will take place from North Sturbridge Road to Podunk Road. Crews will install new utility poles and power lines in Charlton and Sturbridge. Some limited areas of work will also take place on Charlton Road and Picker Road.
Projekvoordele
These upgrades to the electric system in Charlton and Sturbridge will strengthen reliability in the region.
Projekhulpbronne
Nuus en opdaterings
Tydlyn
2023
2024
2025
2026
2027
Projekbetrokkenheid
Spring 2023 – Ongoing
Veldassesserings
Spring 2023 – Ongoing
Toestemming
Spring 2023 – Ongoing
Vegetation Management
01/2025 – 12/2025
Construction and Restoration
Fall 2025 – September 2026