U2 ACR

Transmission Line Project

Mahitungod sa Proyekto

The U2 Transmission Line is 3.5 miles long and runs through Stoughton, Brockton, and Easton. The line was built in the 1970’s and has not had major upgrades since then. This project will add optical ground wire and improve the line’s condition to provide safe and reliable power to customers. Optical ground wire is a type of fiber-optic cable made of steel and aluminum used on overhead power lines to protect them from lightning and carry high-speed data and communication signals. Replacing the power lines will also increase capacity to meet future energy needs.

Mga Benepisyo sa Proyekto

2023
  • Aug - Gate A Approval
2024
2025
  • Feb - Gate B
  • Apr - Kick-Off Meeting
2026
  • Feb - Soil Borings
2027
  • Jan - Gate C Approval
2028
  • Jan - Engineering and Design Completed
  • Apr - Gate C1 Approval
2029
  • Jan - All Permits In Hand
  • Feb - Construction Begins
2030
  • Nov - Overall Ready for Load
  • Dec - Construction Complete
2031
  • Jun - Project Schedule Closed

    * Nagpakita og gikinahanglan nga field

    Mahitungod sa Proyekto

    The U2 Transmission Line is 3.5 miles long and runs through Stoughton, Brockton, and Easton. The line was built in the 1970’s and has not had major upgrades since then. This project will add optical ground wire and improve the line’s condition to provide safe and reliable power to customers. Optical ground wire is a type of fiber-optic cable made of steel and aluminum used on overhead power lines to protect them from lightning and carry high-speed data and communication signals. Replacing the power lines will also increase capacity to meet future energy needs.

    Mga Benepisyo sa Proyekto

    Panahon

    2023
    2024
    2025
    2026
    2027
    2028
    2029
    2030
    2031
    2032
    Gate A Approval
    08/2023 – 08/2023
    Gate B
    02/2025 – 02/2025
    Kick-Off Meeting
    04/2025 – 04/2025
    Soil Borings
    02/2026 – 02/2026
    Pag-apruba sa Ganghaan C
    01/2027 – 01/2027
    Nahuman ang Inhenyeriya ug Disenyo
    01/2028 – 01/2028
    Pag-uyon sa Ganghaan C1
    04/2028 – 04/2028
    All Permits In Hand
    01/2029 – 01/2029
    Konstruksyon
    02/2029 – 12/2030
    Kinatibuk-an Andam na alang sa Karga
    11/2030 – 11/2030
    Project Schedule Closed
    06/2031 – 06/2031