J136S Tap and I135/J136S Mainline

Proyekto

Mahitungod sa Proyekto

J136S Tap Line:

The J136S Tap Line Rebuild Project will improve about 3.1 miles of the existing J136S Tap Line. The line will stay in service as a 115-kilovolt transmission line during the work. The project includes several upgrades. The current line has 42 structures and will be rebuilt with modern steel structures. The new line will be moved about 40 feet east of its current location. Two structures will be removed by re-positioning the lines, leaving a total of 40 structures once the work is complete. The project also includes replacing existing conductors and adding optical ground wire within the current right of way. Vegetation management will increase the maintained area in the right of way by 40-50 feet. The work will also include building new and improved access routes.

Mainline:

As one of the regional electricity providers, National Grid regularly upgrades its equipment to provide reliable electric service to homes and businesses. We are improving part of the electric transmission system to increase reliability, improve communication, and strengthen long-term performance. The project includes updating existing transmission structures and installing new optical ground wire along about 8.1 miles of the I135S/J136S transmission line. The work will replace three existing structures with three H-frame structures, add one new H-frame switch structure, replace some power lines, and install optical ground wire within the current right-of-way. When needed, the project will also include access-road improvements and vegetation management.

Mga Benepisyo sa Proyekto

2024
  • March 2024 - MAINLINE: Soil Borings Completed Begins
  • March 2024 - MAINLINE: Soil Borings Completed Complete
2025
2026
2027
  • January 2027 - TAP LINE: Pre-Construction Activities Begins
  • January 2027 - TAP LINE: Pre-Construction Activities Complete
  • February 2027 - MAINLINE: Pre-Construction Activities Begins
  • February 2027 - MAINLINE: Pre-Construction Activities Complete
  • March 2027 - TAP LINE: Construction Begins
  • Start April 2027 - MAINLINE: Construction Begins
  • November 2027 - TAP LINE: Construction Complete
2028
  • Finish January 2028 - MAINLINE: Construction Complete

Mga Hugna sa Konstruksyon

  1. Pagpangandam sa Lugar

    The first step is clearing trees and brush. This work allows construction crews to safely build access roads and remove trees that could fall onto the power lines.

  1. Mga Kontrol sa Kalikopan

    Next, steps are taken to protect the area during construction. These may include placing mats, silt fences, and containers for construction materials.

  1. Pagtukod Pag-usab sa Linya sa Transmisyon

    New foundations and structures are installed, along with fiber-optic cable and new wires. Old structures are removed, and new wires are energized. Crews use heavy equipment, including cranes.

  1. Pagpahiuli

    Kung mahuman na ang konstruksyon, ibalik sa mga tripulante ang mga gitrabahuan sa ilang orihinal nga kondisyon kutob sa mahimo, gawas kung adunay lain nga gipasabot ang mga permit o kasabutan sa yuta.

Kontaka Kami

If you have any questions, need additional information, would like project materials translated, require interpretation services, or need hard copies of the MEPA filing, please contact Joe Carroll.

    * Nagpakita og gikinahanglan nga field

    Mahitungod sa Proyekto

    J136S Tap Line:

    The J136S Tap Line Rebuild Project will improve about 3.1 miles of the existing J136S Tap Line. The line will stay in service as a 115-kilovolt transmission line during the work. The project includes several upgrades. The current line has 42 structures and will be rebuilt with modern steel structures. The new line will be moved about 40 feet east of its current location. Two structures will be removed by re-positioning the lines, leaving a total of 40 structures once the work is complete. The project also includes replacing existing conductors and adding optical ground wire within the current right of way. Vegetation management will increase the maintained area in the right of way by 40-50 feet. The work will also include building new and improved access routes.

    Mainline:

    As one of the regional electricity providers, National Grid regularly upgrades its equipment to provide reliable electric service to homes and businesses. We are improving part of the electric transmission system to increase reliability, improve communication, and strengthen long-term performance. The project includes updating existing transmission structures and installing new optical ground wire along about 8.1 miles of the I135S/J136S transmission line. The work will replace three existing structures with three H-frame structures, add one new H-frame switch structure, replace some power lines, and install optical ground wire within the current right-of-way. When needed, the project will also include access-road improvements and vegetation management.

    Mga Benepisyo sa Proyekto

    Weather Icon

    The J136S Tap Line construction work will help meet future power needs. Adding optical ground wire will improve communication between substations and make the line more resistant to severe weather, such as lightning. The project will also replace damaged wooden structures with stronger steel structures.

    Panahon

    2024
    2025
    2026
    2027
    2028
    2029
    MAINLINE: Soil Borings Completed
    March 2024 – March 2024
    TAP LINE: Pre-Construction Activities
    January 2027 – January 2027
    MAINLINE: Pre-Construction Activities
    February 2027 – February 2027
    TAP LINE: Construction
    March 2027 – November 2027
    MAINLINE: Construction
    Start April 2027 – Finish January 2028

    Mga Hugna sa Konstruksyon

    1. Pagpangandam sa Lugar

      The first step is clearing trees and brush. This work allows construction crews to safely build access roads and remove trees that could fall onto the power lines.

    1. Mga Kontrol sa Kalikopan

      Next, steps are taken to protect the area during construction. These may include placing mats, silt fences, and containers for construction materials.

    1. Pagtukod Pag-usab sa Linya sa Transmisyon

      New foundations and structures are installed, along with fiber-optic cable and new wires. Old structures are removed, and new wires are energized. Crews use heavy equipment, including cranes.

    1. Pagpahiuli

      Kung mahuman na ang konstruksyon, ibalik sa mga tripulante ang mga gitrabahuan sa ilang orihinal nga kondisyon kutob sa mahimo, gawas kung adunay lain nga gipasabot ang mga permit o kasabutan sa yuta.