Charlton to Sturbridge Interconnection

Progetto

Informazioni sul progetto

The Charlton to Sturbridge Interconnection Project will connect a solar power site in Charlton to National Grid’s electric system. Approximately 3.5 miles of work will take place from North Sturbridge Road to Podunk Road. Crews will install new utility poles and power lines in Charlton and Sturbridge. Some limited areas of work will also take place on Charlton Road and Picker Road.

Benefici del progetto

2023
  • Spring - Project Engagement Begins
  • Spring - Field Assessments Begins
  • Spring - Permitting Begins
2024
2025
  • Jan - Vegetation Management Begins
  • Fall - Construction and Restoration Begins
  • Dec - Vegetation Management Complete
2026
  • September - Construction and Restoration Complete
  • In corso - Coinvolgimento nel progetto completato
  • In corso - Valutazioni sul campo completate
  • Ongoing - Permitting Complete

    * Indica un campo obbligatorio

    Informazioni sul progetto

    The Charlton to Sturbridge Interconnection Project will connect a solar power site in Charlton to National Grid’s electric system. Approximately 3.5 miles of work will take place from North Sturbridge Road to Podunk Road. Crews will install new utility poles and power lines in Charlton and Sturbridge. Some limited areas of work will also take place on Charlton Road and Picker Road.

    Benefici del progetto

    Transmission Line Icon

    These upgrades to the electric system in Charlton and Sturbridge will strengthen reliability in the region.

    Notizie e aggiornamenti

    cronologia

    2023
    2024
    2025
    2026
    2027
    Coinvolgimento nel progetto
    Spring 2023 – Ongoing
    Valutazioni sul campo
    Spring 2023 – Ongoing
    Permitting
    Spring 2023 – Ongoing
    Vegetation Management
    01/2025 – 12/2025
    Construction and Restoration
    Fall 2025 – September 2026