This project will improve the existing electric transmission power line to make it more reliable and enhance communication. The work includes replacing older wooden line structures with new steel structures. Two fiber-optic cables will also be added. These cables help our systems communicate more effectively and protect the line from lightning strikes. This project will also repair existing access roads and build new ones where needed.
 
These improvements will help keep workers safe and make future maintenance easier. All work will take place within or near the existing transmission right-of-way. The project runs through the Massachusetts communities of Ludlow, Palmer, Brimfield, Warren, Brookfield, Sturbridge, and Charlton.

የፕሮጀክት ጥቅሞች

ዜና እና ዝማኔዎች

Information coming soon.

2026
  • Spring 2026 - Soil Testing Begins
  • Spring 2026 - Soil Testing Complete
  • October 2026 - Construction Begins
2027
2028
  • October 2028 - Construction Complete

የግንባታ ደረጃዎች

  1. የጣቢያ ዝግጅት

    የመጀመሪያው እርምጃ ዛፎችን እና ቁጥቋጦዎችን ማጽዳት ነው። ይህ ሥራ የግንባታ ሰራተኞች ወደ ኤሌክትሪክ መስመር የሚገቡ መንገዶችን ደህንነቱ በተጠበቀ ሁኔታ እንዲገነቡ እና ሊወድቁ የሚችሉ ዛፎችን እንዲያስወግዱ ያስችላቸዋል።.

  1. የአካባቢ መቆጣጠሪያዎች

    ቀጥሎም በግንባታ ወቅት አካባቢውን ለመጠበቅ እርምጃዎች ይወሰዳሉ። እነዚህም ምንጣፎችን፣ የጭቃ አጥርን እና ለግንባታ ቁሳቁሶች የኮንክሪት ማጠቢያ ኮንቴይነሮችን ማስቀመጥን ሊያካትቱ ይችላሉ።.

  1. Transmission Line Rebuilding

    አዳዲስ መሠረቶችና መዋቅሮች ከፋይበር-ኦፕቲክ ኬብሎችና ከአዳዲስ ሽቦዎች ጋር ተጭነዋል። አሮጌ መዋቅሮች ይወገዳሉ፣ አዲሶቹ ሽቦዎችም ኃይል ይሰጣቸዋል። ሰራተኞቹ ክሬኖችን ጨምሮ ከባድ መሳሪያዎችን ይጠቀማሉ።.

  1. እድሳት

    After construction, crews restore the work area and return the ground as close as possible to its original condition. (Unless otherwise specified in regulatory requirements or by a landowner).

    * የሚያስፈልግ መስክን ያመለክታል

    ስለ ፕሮጀክቱ

    This project will improve the existing electric transmission power line to make it more reliable and enhance communication. The work includes replacing older wooden line structures with new steel structures. Two fiber-optic cables will also be added. These cables help our systems communicate more effectively and protect the line from lightning strikes. This project will also repair existing access roads and build new ones where needed.
     
    These improvements will help keep workers safe and make future maintenance easier. All work will take place within or near the existing transmission right-of-way. The project runs through the Massachusetts communities of Ludlow, Palmer, Brimfield, Warren, Brookfield, Sturbridge, and Charlton.

    የፕሮጀክት ጥቅሞች

    ዜና እና ዝማኔዎች

    Information coming soon.

    የጊዜ መስመር

    2026
    2027
    2028
    2029
    Soil Testing
    Spring 2026 – Spring 2026
    Construction Start/Complete
    October 2026 – October 2028

    የግንባታ ደረጃዎች

    1. የጣቢያ ዝግጅት

      የመጀመሪያው እርምጃ ዛፎችን እና ቁጥቋጦዎችን ማጽዳት ነው። ይህ ሥራ የግንባታ ሰራተኞች ወደ ኤሌክትሪክ መስመር የሚገቡ መንገዶችን ደህንነቱ በተጠበቀ ሁኔታ እንዲገነቡ እና ሊወድቁ የሚችሉ ዛፎችን እንዲያስወግዱ ያስችላቸዋል።.

    1. የአካባቢ መቆጣጠሪያዎች

      ቀጥሎም በግንባታ ወቅት አካባቢውን ለመጠበቅ እርምጃዎች ይወሰዳሉ። እነዚህም ምንጣፎችን፣ የጭቃ አጥርን እና ለግንባታ ቁሳቁሶች የኮንክሪት ማጠቢያ ኮንቴይነሮችን ማስቀመጥን ሊያካትቱ ይችላሉ።.

    1. Transmission Line Rebuilding

      አዳዲስ መሠረቶችና መዋቅሮች ከፋይበር-ኦፕቲክ ኬብሎችና ከአዳዲስ ሽቦዎች ጋር ተጭነዋል። አሮጌ መዋቅሮች ይወገዳሉ፣ አዲሶቹ ሽቦዎችም ኃይል ይሰጣቸዋል። ሰራተኞቹ ክሬኖችን ጨምሮ ከባድ መሳሪያዎችን ይጠቀማሉ።.

    1. እድሳት

      After construction, crews restore the work area and return the ground as close as possible to its original condition. (Unless otherwise specified in regulatory requirements or by a landowner).