د 301 ACR معرفي کول

د پروژې په اړه

This project will improve the existing electric transmission power line to make it more reliable and enhance communication. The work includes replacing older wooden line structures with new steel structures. Two fiber-optic cables will also be added. These cables help our systems communicate more effectively and protect the line from lightning strikes. This project will also repair existing access roads and build new ones where needed.
 
These improvements will help keep workers safe and make future maintenance easier. All work will take place within or near the existing transmission right-of-way. The project runs through the Massachusetts communities of Ludlow, Palmer, Brimfield, Warren, Brookfield, Sturbridge, and Charlton.

د پروژې ګټې

خبرونه او تازه معلومات

Information coming soon.

2026
  • Spring 2026 - Soil Testing Begins
  • Spring 2026 - Soil Testing Complete
  • October 2026 - Construction Begins
2027
2028
  • October 2028 - Construction Complete

د جوړولو پړاوونه

  1. د ځای چمتووالی

    لومړی ګام د ونو او بوټو پاکول دي. دا کار ساختماني ټیمونو ته اجازه ورکوي چې په خوندي ډول د لاسرسي سړکونه جوړ کړي او هغه ونې لرې کړي چې ممکن د بریښنا لین ته راښکته شي.

  1. د چاپیریال کنټرولونه

    بیا، د ساختماني کارونو په جریان کې د ساحې د ساتنې لپاره ګامونه اخیستل کیږي. پدې کې ممکن د ساختماني موادو لپاره د چتونو، د خټو دیوالونو، او د کانکریټو د مینځلو کانتینرونو ایښودل شامل وي.

  1. Transmission Line Rebuilding

    نوي بنسټونه او جوړښتونه نصب شوي، د فایبر آپټیک کیبلونو او نویو تارونو سره یوځای. زاړه جوړښتونه لرې شوي، او نوي تارونه انرژي شوي دي. عمله د کرینونو په ګډون درانه تجهیزات کاروي.

  1. بیا رغونه

    After construction, crews restore the work area and return the ground as close as possible to its original condition. (Unless otherwise specified in regulatory requirements or by a landowner).

موږ سره اړیکه ونیسئ

    * یو اړین ډګر په ګوته کوي

    د پروژې په اړه

    This project will improve the existing electric transmission power line to make it more reliable and enhance communication. The work includes replacing older wooden line structures with new steel structures. Two fiber-optic cables will also be added. These cables help our systems communicate more effectively and protect the line from lightning strikes. This project will also repair existing access roads and build new ones where needed.
     
    These improvements will help keep workers safe and make future maintenance easier. All work will take place within or near the existing transmission right-of-way. The project runs through the Massachusetts communities of Ludlow, Palmer, Brimfield, Warren, Brookfield, Sturbridge, and Charlton.

    د پروژې ګټې

    خبرونه او تازه معلومات

    Information coming soon.

    مهال ویش

    2026
    2027
    2028
    2029
    Soil Testing
    Spring 2026 – Spring 2026
    Construction Start/Complete
    October 2026 – October 2028

    د جوړولو پړاوونه

    1. د ځای چمتووالی

      لومړی ګام د ونو او بوټو پاکول دي. دا کار ساختماني ټیمونو ته اجازه ورکوي چې په خوندي ډول د لاسرسي سړکونه جوړ کړي او هغه ونې لرې کړي چې ممکن د بریښنا لین ته راښکته شي.

    1. د چاپیریال کنټرولونه

      بیا، د ساختماني کارونو په جریان کې د ساحې د ساتنې لپاره ګامونه اخیستل کیږي. پدې کې ممکن د ساختماني موادو لپاره د چتونو، د خټو دیوالونو، او د کانکریټو د مینځلو کانتینرونو ایښودل شامل وي.

    1. Transmission Line Rebuilding

      نوي بنسټونه او جوړښتونه نصب شوي، د فایبر آپټیک کیبلونو او نویو تارونو سره یوځای. زاړه جوړښتونه لرې شوي، او نوي تارونه انرژي شوي دي. عمله د کرینونو په ګډون درانه تجهیزات کاروي.

    1. بیا رغونه

      After construction, crews restore the work area and return the ground as close as possible to its original condition. (Unless otherwise specified in regulatory requirements or by a landowner).

    موږ سره اړیکه ونیسئ

      * یو اړین ډګر په ګوته کوي