Mystic to Everett Line Replacement

Project

প্ৰকল্পটোৰ বিষয়ে

The Mystic to Everett Line Replacement Project is a joint project between National Grid and Eversource. The goal of the project is to upgrade underground power equipment between a National Grid substation in Everett and Eversource’s Mystic Substation in Boston. The project will take place between the cities of Everett and Boston.

By updating sections of underground power cables, the project will help make electric service more reliable for customers. The work will require some roadway construction. The areas most affected are expected to begin near the intersection of Horizon Way and Broadway and continue about half a mile south toward Alford Street in Boston.

2025
  • Q3 2025 - Massachusetts DPU Filing Begins
  • Q3 2025 - Massachusetts DPU Filing Complete
2026
  • Q1 2026 - Construction Start Begins
  • Q1 2026 - Construction Start Complete
2027
  • Q2 2027 - Estimated In-Service Date Begins
  • Q2 2027 - Estimated In-Service Date Complete

আমাৰ সৈতে যোগাযোগ কৰক

    * এটা প্ৰয়োজনীয় ক্ষেত্ৰ সূচায়

    প্ৰকল্পটোৰ বিষয়ে

    The Mystic to Everett Line Replacement Project is a joint project between National Grid and Eversource. The goal of the project is to upgrade underground power equipment between a National Grid substation in Everett and Eversource’s Mystic Substation in Boston. The project will take place between the cities of Everett and Boston.

    By updating sections of underground power cables, the project will help make electric service more reliable for customers. The work will require some roadway construction. The areas most affected are expected to begin near the intersection of Horizon Way and Broadway and continue about half a mile south toward Alford Street in Boston.

    টাইমলাইন

    2025
    2026
    2027
    2028
    Massachusetts DPU Filing
    Q3 2025 – Q3 2025
    নিৰ্মাণ আৰম্ভ
    Q1 2026 – Q1 2026
    Estimated In-Service Date
    Q2 2027 – Q2 2027

    আমাৰ সৈতে যোগাযোগ কৰক

      * এটা প্ৰয়োজনীয় ক্ষেত্ৰ সূচায়