Lawrence #1

Substation Project

About the Project

The Lawrence #1 substation was built in 1944 and needs to be rebuilt because the equipment is aging and the station cannot meet current power needs. To fix these issues and support growing electric demand, a new substation will be built next to the existing one, which will then be retired. The project will also include necessary upgrades to the existing overhead power poles and wires, as well as the installation of new underground electrical equipment to accommodate the new substation.

Project Benefits

Project Resources

2024
  • Jan - Electric distribution line upgrades Begins
  • Aug - Substation rebuild Begins
2025
2026
2027
2028
  • Jun - Electric distribution line upgrades Complete
  • Jun - Substation rebuild Complete

Frequently Asked Questions

7 FAQs

The purpose of the Lawrence #1 D-Substation Rebuild and D-Line Upgrade is to rebuild the existing Lawrence #1 substation and to strengthen the electric distribution system to serve our customers more reliably.

Substation construction will include deliveries of equipment to and from the site located on S Canal Street. Crews will be constructing new foundations and installing new electrical equipment as part of the substation rebuild, and ultimately removing existing equipment. In addition, work will be performed along public roadways as crews will be installing new electrical equipment such as poles and wires. Local police details and lane restrictions will be used to help ensure the safety of our crews and the general public.
 
There will be limited power outages associated with this work. You will be notified well in advance of any planned outages that may impact your service. You may notice that the old poles will remain for a period of time following completion of work. National Grid coordinates closely with other local utilities to transfer their assets from the old pole to the new pole. Once all the transfers have occurred, the old poles can safely be removed.

While the substation construction will occur on land that is adjacent to the National Grid substation on S Canal Street, most of the work will occur along the public roadway. The work areas where crews will be most noticeable include:
 
Shepard Street, Andover Street, Beacon Street, Everett Street, Rowe Street, Newton Street, Salem Street, Kingston Street, Durham Street, Atkinson Street, Emmett Street, Sanborn Street, Shattuck Street, Carver Street, Merrimack Street, Market Street, Blanchard Street, Parker Street, Baily Street, Abbot Street, Springfield Street, Salem Street, Farnham Street, Andover Street, Boxford Street, Abbot Street, Loring Street, Greenfield Street, Portland Street, Market Street, Phillips Street, Newton Street, S Broadway, RR Crossing, Winthrop Avenue, S. Union Street, Cambridge Street, Prospect Street, Martson Street, Canal Street, and spanning the Merrimack River.

The existing Lawrence #1 substation was built in 1944 and is nearing the end of life, therefore a substation rebuild is needed to ensure electric reliability. To incorporate the new substation, upgrades are required to much of the existing overhead infrastructure (poles and wires) as well as some underground infrastructure. The work completed on this project will enable us to serve our customers more reliably throughout Lawrence.

Electric distribution line upgrades began in January of 2024 and the substation rebuild will begin in Fall of 2024. Both are scheduled to be complete by June 2028.

National Grid is undertaking extensive community outreach to inform neighbors, public officials, and other stakeholders about the project.

If you have any questions or concerns about the project, please contact:
 

Eric Sacchetti | Stakeholder Management

Email: [email protected] | Phone: +1-781-570-1228

    * Indicates a required field

    About the Project

    The Lawrence #1 substation was built in 1944 and needs to be rebuilt because the equipment is aging and the station cannot meet current power needs. To fix these issues and support growing electric demand, a new substation will be built next to the existing one, which will then be retired. The project will also include necessary upgrades to the existing overhead power poles and wires, as well as the installation of new underground electrical equipment to accommodate the new substation.

    Project Benefits

    Improve electric reliability in Lawrence.

    Provide better service.

    Improve how efficiently the system operates.

    Project Resources

    News and Updates

    Timeline

    2024
    2025
    2026
    2027
    2028
    2029
    Electric distribution line upgrades
    01/2024 – 06/2028
    Substation rebuild
    08/2024 – 06/2028

    Frequently Asked Questions

    7 FAQs

    The purpose of the Lawrence #1 D-Substation Rebuild and D-Line Upgrade is to rebuild the existing Lawrence #1 substation and to strengthen the electric distribution system to serve our customers more reliably.

    Substation construction will include deliveries of equipment to and from the site located on S Canal Street. Crews will be constructing new foundations and installing new electrical equipment as part of the substation rebuild, and ultimately removing existing equipment. In addition, work will be performed along public roadways as crews will be installing new electrical equipment such as poles and wires. Local police details and lane restrictions will be used to help ensure the safety of our crews and the general public.
     
    There will be limited power outages associated with this work. You will be notified well in advance of any planned outages that may impact your service. You may notice that the old poles will remain for a period of time following completion of work. National Grid coordinates closely with other local utilities to transfer their assets from the old pole to the new pole. Once all the transfers have occurred, the old poles can safely be removed.

    While the substation construction will occur on land that is adjacent to the National Grid substation on S Canal Street, most of the work will occur along the public roadway. The work areas where crews will be most noticeable include:
     
    Shepard Street, Andover Street, Beacon Street, Everett Street, Rowe Street, Newton Street, Salem Street, Kingston Street, Durham Street, Atkinson Street, Emmett Street, Sanborn Street, Shattuck Street, Carver Street, Merrimack Street, Market Street, Blanchard Street, Parker Street, Baily Street, Abbot Street, Springfield Street, Salem Street, Farnham Street, Andover Street, Boxford Street, Abbot Street, Loring Street, Greenfield Street, Portland Street, Market Street, Phillips Street, Newton Street, S Broadway, RR Crossing, Winthrop Avenue, S. Union Street, Cambridge Street, Prospect Street, Martson Street, Canal Street, and spanning the Merrimack River.

    The existing Lawrence #1 substation was built in 1944 and is nearing the end of life, therefore a substation rebuild is needed to ensure electric reliability. To incorporate the new substation, upgrades are required to much of the existing overhead infrastructure (poles and wires) as well as some underground infrastructure. The work completed on this project will enable us to serve our customers more reliably throughout Lawrence.

    Electric distribution line upgrades began in January of 2024 and the substation rebuild will begin in Fall of 2024. Both are scheduled to be complete by June 2028.

    National Grid is undertaking extensive community outreach to inform neighbors, public officials, and other stakeholders about the project.

    If you have any questions or concerns about the project, please contact:
     

    Eric Sacchetti | Stakeholder Management

    Email: [email protected] | Phone: +1-781-570-1228

      * Indicates a required field