Spencer to Webster Transmission

Project

About the Project

The 17-mile-long Spencer to Webster Transmission Project, also known as the T20 Line Asset Condition Replacement Project, replaces the existing 69-kilovolt transmission line through the municipalities of Spencer, Charlton, Dudley, and Webster. The project plans to replace all existing wood-pole structures with steel structures between the Meadow Street Substation in Spencer and the East Webster Substation in Webster. The transmission infrastructure will be built to 115-kilovolt standards but will initially operate at 69 kilovolts until additional capacity is needed.
 
Construction is expected to take place from early 2030 to early 2032. Final restoration efforts are expected to continue into early Summer 2032. Public outreach in these communities has been ongoing. This project is currently in the planning phase and is awaiting permitting approvals.

Project Benefits

2025
  • 2025 - Permitting Begins
2026
2027
2028
2029
  • 2029 - Permitting Complete
2030
  • Q1 2030 - Constuction Begins
2031
2032
  • Q2 2032 - In-Service Begins
  • Q2 2032 - Constuction Complete
  • Q2 2032 - In-Service Complete

    * Indicates a required field

    About the Project

    The 17-mile-long Spencer to Webster Transmission Project, also known as the T20 Line Asset Condition Replacement Project, replaces the existing 69-kilovolt transmission line through the municipalities of Spencer, Charlton, Dudley, and Webster. The project plans to replace all existing wood-pole structures with steel structures between the Meadow Street Substation in Spencer and the East Webster Substation in Webster. The transmission infrastructure will be built to 115-kilovolt standards but will initially operate at 69 kilovolts until additional capacity is needed.
     
    Construction is expected to take place from early 2030 to early 2032. Final restoration efforts are expected to continue into early Summer 2032. Public outreach in these communities has been ongoing. This project is currently in the planning phase and is awaiting permitting approvals.

    Project Benefits

    Transmission Line Icon

    Modernizing the existing transmission lines by replacing all wood structures with steel structures mitigates future woodpecker activity.

    Hardhat Icon

    The new line configuration will enhance system reliability by significantly reducing the likelihood of vegetation-related outages.

    Cityscape Icon

    The project will provide additional transmission capacity and voltage support to meet increasing electricity demand by rebuilding the line to 115-kilovolt standards.

    Timeline

    2025
    2026
    2027
    2028
    2029
    2030
    2031
    2032
    2033
    Permitting
    2025 – 2029
    Constuction
    Q1 2030 – Q2 2032
    In-Service
    Q2 2032 – Q2 2032

      * Indicates a required field