323 ACR

About the Project

The 302 and 323 transmission lines, both 345,000 kilovolts, were first built in 1968 to connect the Carpenter Hill and Medway substations. Part of this line is now called the 323 line. The section owned by National Grid runs about 14.4 miles, from the Millbury #3 substation to the Milford/Medway town line.

Today, the 323 line includes 153 wooden poles and 14 steel poles. The steel poles show signs of aging, including light rust and wear near their bases. The wooden poles are in worse condition and have problems such as rot, cracking, bending, and damage from woodpeckers. Almost every wooden pole has some level of damage.

This project will upgrade the transmission line by replacing all existing wooden poles with new steel poles designed to last longer. Crews will also install new fiber-optic ground wires and replace insulators and other equipment. These improvements will help make the electric system safer, more reliable, and better prepared for the future.

Project Benefits

2020
  • Early - Engineering Begins
2021
2022
  • Early Summer - Soil Borings Begins
  • Late Summer - Soil Borings Complete
2023
2024
2025
  • Dec - Construction Start Begins
2026
  • Late - Engineering Complete
  • TBD - Construction Start Complete

Phases of Construction

  1. What to Expect

    Electric Transmission improvements take place in several phases. The descriptions below show common construction steps, but the exact process and materials may vary.

  2. Site Preparation

    The first step is clearing trees and brush. This work allows construction crews to safely build access roads and remove trees that could fall onto the power lines.

  1. Environmental Controls

    Next, steps are taken to protect the area during construction. These may include mats, silt fences, and containers for construction materials.

  1. Transmission Line Rebuilding

    Crews use heavy equipment, including cranes. New foundations and structures are installed, along with fiber-optic cables and new wires. Lastly, old structures are removed, and the lines are powered.

  1. Restoration

    After construction, crews restore the work area and return the ground as close as possible to its original condition, unless otherwise specified by regulatory requirements or agreement with a landowner.

    * Indicates a required field

    About the Project

    The 302 and 323 transmission lines, both 345,000 kilovolts, were first built in 1968 to connect the Carpenter Hill and Medway substations. Part of this line is now called the 323 line. The section owned by National Grid runs about 14.4 miles, from the Millbury #3 substation to the Milford/Medway town line.

    Today, the 323 line includes 153 wooden poles and 14 steel poles. The steel poles show signs of aging, including light rust and wear near their bases. The wooden poles are in worse condition and have problems such as rot, cracking, bending, and damage from woodpeckers. Almost every wooden pole has some level of damage.

    This project will upgrade the transmission line by replacing all existing wooden poles with new steel poles designed to last longer. Crews will also install new fiber-optic ground wires and replace insulators and other equipment. These improvements will help make the electric system safer, more reliable, and better prepared for the future.

    Project Benefits

    This project improves the transmission line by replacing worn out wooden poles and an aging shield wire. The upgrades will help provide safe and dependable electric service to customers and strengthen the local transmission system. The improvements will also extend the life of the line, helping it serve the community for many years to come.

    Timeline

    2020
    2021
    2022
    2023
    2024
    2025
    2026
    2027
    Engineering
    2020 – 2026
    Soil Borings
    Early Summer – Late Summer
    Construction Start
    12/2025 – TBD

    Phases of Construction

    1. What to Expect

      Electric Transmission improvements take place in several phases. The descriptions below show common construction steps, but the exact process and materials may vary.

    2. Site Preparation

      The first step is clearing trees and brush. This work allows construction crews to safely build access roads and remove trees that could fall onto the power lines.

    1. Environmental Controls

      Next, steps are taken to protect the area during construction. These may include mats, silt fences, and containers for construction materials.

    1. Transmission Line Rebuilding

      Crews use heavy equipment, including cranes. New foundations and structures are installed, along with fiber-optic cables and new wires. Lastly, old structures are removed, and the lines are powered.

    1. Restoration

      After construction, crews restore the work area and return the ground as close as possible to its original condition, unless otherwise specified by regulatory requirements or agreement with a landowner.

      * Indicates a required field