S145E/T146E ACR & OPGW Installation

Project

About the Project

The S145E/T146E Asset Condition Replacement and OPGW Installation Project will replace older overhead transmission structures along an 8-mile area between Wakefield and Salem. Both the S and T lines begin at the Wakefield Junction Substation and end at the Canal Street Substation in Salem. Each line is about 8.3 miles long and runs side by side through the towns of Wakefield, Lynn, Peabody, and Salem.

Project Benefits

2028
  • November 2028 - Construction Begins
2029
2030
2031
2032
  • January 2032 - Construction Complete
  • June 2032 - Project Closeout Begins
  • June 2032 - Project Closeout Complete

    * Indicates a required field

    About the Project

    The S145E/T146E Asset Condition Replacement and OPGW Installation Project will replace older overhead transmission structures along an 8-mile area between Wakefield and Salem. Both the S and T lines begin at the Wakefield Junction Substation and end at the Canal Street Substation in Salem. Each line is about 8.3 miles long and runs side by side through the towns of Wakefield, Lynn, Peabody, and Salem.

    Project Benefits

    Installing optical ground wire (OPGW) and replacing older wooden structures will improve the flow of electricity and help National Grid provide more reliable service to northern Boston.

    Timeline

    2028
    2029
    2030
    2031
    2032
    2033
    Construction
    November 2028 – January 2032
    Project Closeout
    June 2032 – June 2032